ADDIS ABABA, Ethiopia
Ethiopia
has refuted claims it has begun filling the Grand Ethiopian Renaissance Dam (GERD),
just days after talks with Sudan and Egypt failed to reach agreement on how to
regulate the flow of the Nile waters from the reservoir.
In a statement on Thursday, Addis
Ababa said the amount of water flowing downstream, to Sudan and Egypt, had predictably
reduced after the dam structure was raised, absorbing more of the incoming
water.
The Ethiopian Water,
Irrigation and Energy Minister, Dr Seleshi Bekele, the said his country had not
blocked the flow of water as earlier claimed.
“The GERD construction has
reached level 560m compared to level 525m last year this time. The inflow into
the reservoir due to heavy rainfall and runoff exceeded the outflow and created
natural pooling. This continues until overflow is triggered soon,” Dr Seleshi
said.
“The dam is yet to be
constructed to level 640m in the following years. In fact, predicted heavy rain
this year is expected to cause huge flooding in the region.”
Ethiopia’s comment comes
after Sudan on Wednesday claimed the volume of water reaching its territory had
reduced and accused Addis Ababa of filling the dam without reaching an
agreement.
Both Sudan and Egypt have
raised concerns that the mega-dam project could see their countries face water
shortages since millions of their citizens depend on the Nile for livelihood.
Khartoum’s Ministry of
Irrigation and Water Resources said on Wednesday that the volume in the Nile
had gone down by as much as 90 million cubic metres of water per day,
attributing it to the closure of the GERD gates.
“Local and international
media circulated information and pictures taken by satellites indicating that
Ethiopia started filling the Renaissance Dam before reaching an agreement on
the first filling and operation," said the ministry, adding that it tasked
its agencies specialised in measuring the levels of the Blue Nile to
investigate the authenticity of the information.
“It was evident through the
flow measures of water at Al-deem station near the Ethiopian border that there
is a decline in water levels equivalent to 90 million cubic meters per day,
that is confirming the closure of the gates of GERD.”
Sudan raised the alarm as
Egypt sought “urgent clarification” on the reports that Addis Ababa had begun
filling the dam.
Officially, Ethiopia
maintains it has a sovereign right to fill the dam, even before the three
countries agree on technical arrangements of the filling.
The $4.5 billion mega-dam is
projected to have a capacity of 6.4GW power when complete. Ethiopia says the
project has reached a stage to start the initial storage process estimated at
4.9 billion cubic metres out of its 74 billion cubic metres capacity.
On Tuesday, the three
countries failed to agree on technical and legal details regarding the rules
for filling and operating the dam.
Sudan said it sent its final
report on the GERD to the African Union following an end to negotiations and
included a draft of “balanced and fair agreement” that it says is suitable to
be the basis for a comprehensive tripartite pact.
Egypt fears the dam will
deny it its annual share of the Nile's water, and demands an agreement on
files, including the safety of the dam and the setting of rules for filling it
in times of drought.
Ethiopia sees the hydroelectric project as important for its economic growth.